Pool removal in South Dakota

Pool removal in South Dakota starts with a local permit and an 811 call before digging; then a crew paid South Dakota rates fills the pool in or takes it out.

Concrete pool, filled in · 1–3 days
$2,200–$8,800
Concrete pool, taken out · 3–7 days
$3,500–$14,000

US ranges from Angi, set for South Dakota construction pay (BLS, May 2025); days from HomeAdvisor.

Pool removal cost calculator

Prices are US averages.

What kind of pool is it?

Not sure? Touch the wall: soft and pressable is vinyl, slick and glossy is fiberglass, rough is concrete.

Most pool removal jobs in South Dakota take a week or less, and the price depends on whether you fill the pool in or take it all the way out. One call gets a local crew to your yard with a written price. Before digging, South Dakota requires advance notice to the one-call center, and local permit requirements depend on where you live. Filling in a concrete pool takes about 1 to 3 days Removing a concrete pool completely takes about 3 to 7 days

What does each kind of pool cost?

South Dakota prices start from Angi's 2026 national prices, adjusted for local pay, where the average construction laborer makes $21.30 an hour versus $25.02 nationwide.

Pool typeWork involvedSouth Dakota range
Above groundTaken apart and hauled away$425 to $2,200
Concrete or guniteFilled in place$2,200 to $8,800
Concrete or guniteDug out completely$3,500 to $14,000
FiberglassRemoved$4,400 to $13,200
Vinyl linerRemoved$2,600 to $8,800

Filling in a concrete pool costs less and takes less time than removing it completely. Full removal takes the entire pool out of the ground, so it runs higher and needs more time. Once a crew walks your yard, they can hand you a price in writing, and getting that visit set up takes one call.

Permits for taking out a pool

Each city sets its own permit rules. In Sioux Falls, the razing permit for demolition work is a flat $40.

Rapid City's demolition permit application asks you to confirm the job clears out all footings, foundations, rubble, and debris. The excavation also has to be filled properly.

A Sioux Falls pool hooked up to a city utility can't come out until that service is disconnected and capped. That means getting a sewer and water capping permit ahead of time.

Calling 811 before any digging

Under South Dakota law, no digging can happen until the one-call center gets at least 48 hours' notice. The clock starts at 12:01 a.m. on the day after you call, and weekends and state holidays don't count. Call on a Thursday, for instance, and the waiting period stretches into the next week.

Draining the pool water

According to the state's environmental agency, pool water may need up to 10 days to shed its chlorine naturally. If you stop adding chlorine and wait 10 days, you can drain the pool without an individual discharge permit, as long as you follow the state's guidance on pool water.

Draining into a storm sewer takes the city's approval first, plus a water sample. Chlorine must read below 0.05 mg/L before draining starts, and the water can't contain floating solids or overwhelm the storm sewer.

Hiring a crew and licensing

Anyone performing construction services in South Dakota must carry a state contractor's excise tax license, with construction receipts taxed at 2%. This is a tax license, not evidence of trade skill.

Homeowners in Sioux Falls don't need a contractor license themselves. Even so, the building permits are on you, along with code compliance and inspections. Ask about permits and inspections when the crew visits your yard and prepares your written price.

Have a crew come see your yard?

One call reaches a pool demolition company that works in your area. They'll ask about your pool and yard, book a visit and give you a price in writing, so you know your real cost instead of a range. With the 811 wait and up to 10 days to dechlorinate, the sooner you call, the sooner the pool is gone. Call now.

Get a crew to look at your yard

The ranges tell you what is usual. Once a crew sees your pool, the access, and the fill, they will give you a real written quote.